Roadmap

Milestone: Design

4 months late (12/31/2020 10:59:00 PM)

43%

Number of tickets:
closed:
3
active:
4
Total:
7

This milestone is complete when the high level design of the system is complete. This includes the two critical software interfaces as well as the requirements, architecture, and design documents.

Milestone: Raw Generator

3 months late (01/31/2021 10:59:00 PM)

50%

Number of tickets:
closed:
1
active:
1
Total:
2

This milestone is complete when a prototype raw generator has been built and tested successfully to generate random looking bits.

Milestone: Link

3 months late (02/19/2021 10:59:00 PM)

33%

Number of tickets:
closed:
1
active:
2
Total:
3

This milestone is complete when the Driver can communicate with the Generator over the USB Link.

Milestone: Statistical Tests

7 weeks late (03/25/2021 11:59:00 PM)

33%

Number of tickets:
closed:
1
active:
2
Total:
3

This milestone is complete when the statistical testing component is operational and the generator passes the tests.

Milestone: Final Presentation

12 days late (04/29/2021 11:59:00 PM)

Note: See TracRoadmap for help on using the roadmap.